Quantity & cost estimation - Rate analysis || Farm Structure and Surveying by Er Padam Prasad Paudel

Quantity & cost estimation - Rate analysis || Farm Structure and Surveying by Er Padam Prasad Paudel

Agricultural Engineering

54 года назад

181 Просмотров

This video is contents the lectures related to 'Estimation and Costing' topic of Subject Farm Structure and Surveying AEN403, under the curriculum of Bachelor of Agriculture (BSC Ag) agriculture and Forestry (AFU), Institute of Agriculture and Animal Science (IAAS) under Tribhuvan University (TU) or Purwanchal University (PU) or Farwestern Universtity (FWU) of Nepal

This is Part two of Estimation and costing Topic. Part 1 can be accessed through https://youtu.be/QwP1ugxYP3Y?si=LR8eSYNwXEmSNlJc
In this video teacher explain about the Quantity Estimations, Cost estimations, Rate analysis, and some practical scenario related to topic.

Quantity & cost estimation - Rate analysis || Farm Structure and Surveying, AEN403; lecture by Er Padam Prasad Paudel ( Padam sir, Padam Poudel, Padam Paudel)

Lecture covers following numerical:
1. Determine the quantity of materials required to construct RCC slab of 20m * 15m * 0.12m with M20 concrete.
2. Estimate the quantities of required for preparing 10m3 of PCC in 1:2:4.
3. Calculate the quantities of materials required to construct an RCC slab of 25 m x 10 m x 0.13m in M15 concrete with 1% steel bars.
4. Calculate the quantities of cement, sand and gravel required to prepare 81 cu. Ft of concrete having 1:3:4 as the proportion of aggregates
5. Determine the quantity of materials required to plaster 90m long 4m high wall on both side in 1:5 cement sand mortar 12.5mm thick.
6. Analyze rate to prepare 1:3:6 PCC works. (Skilled and unskilled labor needed to prepare 1 cum of PCC works is 1 and 5. Assume suitable rate)
7. Analyze the rate for Providing and laying of 12.5 mm. thick cement sand plaster work in 1:4 ratios.
8. Workout the per square metre cost for plastering in CM 1:3 - 12 mm thick for ceilings.

Chapters
0:00 Quantities estimate for concrete
21:38 Assignment questions
30:00 Rate Analysis Theory
34:56 Rate Analysis Numericals
41:48 Rate analysis Practical

This lecture was recorded on the online class and shared here for the welfare of students studying BSc Ag program in Nepal. And it is also a important topic for Civil Engineering and Agricultural Engineering students.

Term used: #rateanalysis #FarmSurvey #FarmStructure #PadamPrasadPaudel #estimationandcosting #BOQ #quantitysurvey Boq civil engineering works, quantity surveying in civil engineering

This lecture is based on syllabus of
AFU BSc Ag Seventh 7th Semester 's Farm Structure and Surveying, AEN 403
TU IAAS BSc Ag Eighth 8th Semester 's Farm Structure and Surveying , AEN 421

Тэги:

#Farm_Structure #BSC_Ag #AFU #IAAS #TU #Farm_Survey #AEN_403 #Centre_line_methods #Long_wall_and_short_wall_methods #Detail_Estimate #Approximate_estimate #Estimating_and_Costing_of_Agricultural_Structures #Padam_sir #Padam_Poudel #Padam_Prasad_Poudel #Analysis_of_rates #Methods_of_taking_out_quantities #Agri_Engineering #Rate_analysis #Cost_estimation #Quantity_estimation #Norms_and_specifications #Engineering_drawing #Farm_buildings #civil_engineering #Dharma_raj_Bagale #BOQ
Ссылки и html тэги не поддерживаются


Комментарии: